M4/M6 Kilcock - Kinnegad Motorway
Under the Government announcement of the pilot projects on 1st June 1999 this project was to be assessed by the NRA for its suitability to be advanced as a PPP. Subsequently the project was included as one of the projects approved under Tranche II of the PPP Roads programme as announced by the NRA in June 2000. The project involved the construction of 39 km of motorway from Kinnegad to Kilcock and is an extension of the Kilcock-Maynooth-Leixlip motorway on the N4/N6 Sligo/Galway to Dublin route. The Motorway by-passes the towns of Enfield and Kinnegad.
The PPP contract was awarded in March 2003 to the EuroLink Consortium (SIAC Construction Ltd and Cintra - Concesiones de Infraestrucutras de Transporte S.A.).
Contract Award Date | Contract Awarded to | PPP Type | Government Programme | Status |
---|---|---|---|---|
March 2003 | Eurolink Consortium | Concession | National Development Plan 2000 - 2006 | Opened 2005 |
For further information relating to this road please contact Eurolink on 046 954 0266
Please click here for the M4 Eurolink website
Financial Aspects of the M4/M6 Kinnegad-Kilcock Motorway PPP Contract |
---|
Concession Company at Contract AwardThe EuroLink consortium comprises SIAC Construction Limited, an Irish construction company, and Cintra - Concesiones de Infraestrucutras de Transporte S. A., a major Spanish company with road concession interests in Spain, Portugal, Canada and Chile. |
Duties and obligations of the Concession CompanyFor the 39 km motorway scheme, including 19 overbridges, 7 underbridges, and 3 underpasses, Eurolink is required to carry to undertake the following tasks:
|
Period of ConcessionThe contract was signed on the 24th March 2003 and will extend for 30 years from that date. The construction is anticipated to take approximately 3.5 years and EuroLink will be responsible for collection of tolls for a period of approximately 26.5 years. |
Cost of the projectThe Authority estimates that if it were to undertake itself all the design, construction, maintenance, operation and re-investment tasks that are being required of Eurolink the cost would be in the order of €550m in 2003 values. The Authority estimates that the cost of land, preliminary studies/design necessary to identify the route, preparation of the statutory documents (Motorway scheme and Environmental Impact Statement), advance ground investigation, initial archaeological testing and resolution, and supervision of its construction will amount to approximately €64m. These costs apply irrespective of the contractual means that could be employed for the delivery of the scheme. |
Eurolink's FinancingEurolink has arranged funding from three sources:
EuroLink is the party responsible for the repayment of these debts. 1Post financial close debt was syndicated to three further banks - Banco Português de Investimento (Banco BPI - a Portuguese bank), Banco San Paulo (an Italian bank), and Instituto de Credito Official (ICO - a Spanish bank). |
Payments from the Authority to EurolinkThe Authority’s payments to Eurolink are fixed and consist of payments of €146m (2003 values) over the period of the construction, released on satisfactory completion of key construction elements, and €6m (2003 values) in total in the period of operation. |
Payments from Eurolink to the AuthorityEuroLink will pay a share to the Authority, dependent on the level of traffic on the road, of the toll revenues collected. Without divulging full details due to the commercial sensitivity of the exact proposal, the Authority anticipates that this revenue share will be a very substantial amount of money that will part repay the subvention payments that the Authority will have made and will be payable during the period of the concession. |
Payments from Eurolink to the StateIn addition to the revenue share that it will pay to the Authority, EuroLink will be obliged to make the following payments:
As with the revenue share, the Authority does not wish to state the estimated amount of these payments but can confirm that they will amount to a substantial amount of money. |
Summary OverviewFor infrastructure with an estimated cost of €550m excluding land/preparatory costs, the State will pay €152m excluding land/preparatory costs and will recoup very substantial monies by means of revenue share, rates and taxes. |